Phase 2 Development of JDA Block B-17

Owner:
Carigali – PTTEPI Operating Company SDN. BHD. (CPOC)

Scope of Work:
Engineering, Procurement, Construction, Transportation and Installation, And Offshore Hookup and Commissioning (EPCIC)

Project Duration:
August 2011 to March 2013

Project Detail

Phase 2 development involves two satellite Well Head Platform (MDE and JKB) in Block 17 Gas Field. JKB is 16 slot well head platform installed about 6 Km from existing wellhead platform. Multiphase Production from JKB will be transferred via new 18" subsea pipeline to commingle with JKA production and delivered to MDPP via existing 24" subsea pipeline.