Our Project

Over 160 platforms in Southeast Asian waters, including Thailand, Malaysia and Myanmar have been delivered by TNS with full EPCIC contracts providing Project Management, Engineering, Procurement, Construction, Installation, and Commissioning for Offshore Oil and Gas Operators.
And now TNS have been expanding our business area to onshore plant EPC service such as Factory, Power-generation facility, Module Fabrication, Steel structure Fabrication, and operational support and Maintenance services in both onshore and offshore.



JDA BLOCK B-17 FIELD DEVELOPMENT PROJECT (PHASE 5)

Client : CPOC (CARIGALI-PTTEPI OPERATING COMPANY SDN BHD)

Scope of Work : Engineering, Procurement, Construction, Onshore Pre-Commissioning, Load-out & Sea fastening, Offshore Transportation & Installation, Offshore Hook-up and Commissioning (EPCIC)

Project duration : October 2020 – April 2022

 

Bundled Phases 3 Project

Client : PTT Exploration and Production Public Company Limited

Scope of Work : Engineering, Procurement, Construction, Transportation and Installation of WHPs, associated pipelines, and tie-in work

Project duration : February  2021 to December 2026

PROVISION OF CALL OUT ENGINEERING SUPPORT SERVICES 2021-2023

Client:

MEDCO ENERGI THAILAND (BUALUANG) LIMITED

Scope of Work:

Provision of Engineering support services for Bualuang field, Gulf of Thailand

Project duration:

2 years (June 2021 – June 2023)

Bundled Phases 2, EPCI Of Wellhead Platforms, Associated Pipelines, Brownfield Modifications and Tie-ins.

Client:
PTT EXPLORATION AND PRODUCTION PUBLIC COMPANY LIMITED “PTTEP”

Scope of Work:
Engineering, Procurement, Construction, Transportation and Installation of Wellhead Platforms, Associated Pipelines, Tie-in Work, Brownfield Modification Work including Provision of Wye/ Plem.

Project Duration:
September 2015 – October 2021

Phase 2 Development of JDA Block B-17

Owner:
Carigali – PTTEPI Operating Company SDN. BHD. (CPOC)

Scope of Work:
Engineering, Procurement, Construction, Transportation and Installation, And Offshore Hookup and Commissioning (EPCIC)

Project Duration:
August 2011 to March 2013

Yetagun Phase 4 Development Project

Owner:
Petronas Carigali Myanmar (Hongkong) Limited (PCML)

Scope of Work:
Engineering, Procurement, Construction & Commissioning

Project Duration:
July 2009 to October 2011